Basic Checklist for Successful Commissioning

Commissioning Checklist

This checklist guides through the technical commissioning of Kentix components and KentixONE: preparation, installation, initial configuration, testing and handover to operations.

Project Data​

Project name: _________________________________

Contact person: _________________________________

Customer number: _________________________________

Order no.: _________________________________

Location: _________________________________

Address: _________________________________

Date: _________________________________

Version: _________________________________

Additional notes: _________________________________

Preparations​

  • Check release notes/device notes; provide appropriate firmware packages and licenses.
  • Define network and power topology:
  • PoE/power supply, IP addressing, VLAN concept, wireless/bus (BLE, 868 MHz).
  • Ensure construction site requirements:
  • Communication options available; Support availability known; pre-register booked support assistance.
  • TeamViewer installed on commissioning PC; access to software updates available; cloud licenses activated (if needed).
  • On-site conditions and technical documentation/floor plans are available.
  • Requirements specification for needed functionality exists.
  • Knowledge and resources:
  • Familiar with software and hardware; required skill level (electrical engineering, network, mechanics) available or specialists contracted.
  • Components and tests:
  • All required components complete and functional; special technical configurations pre-built and tested.
  • Customer network:
  • Fully functional; for VLANs: pre-configured, ports/VLAN assignments known.
  • Firewalls: Port 443 inbound and outbound open or rules exist; all devices reachable.
  • Manageable PoE switches ideal; access credentials available.
  • Available IP addresses and network parameters (netmask, gateway) defined; required passwords/access known.
  • External services prepared: Email/SMTP, LDAP/AD, VDS etc. Access credentials available.
  • KentixONE central unit (SiteManager or Docker) installed first; internet access available; KentixONE license installed/activated.
  • Software versions: Keep all devices (central and satellites) at identical software version.
  • Sub-minor updates (e.g. 8.5.x) perform right after adding in KentixONE.
  • Minor updates (e.g. 8.x.x) perform directly on device before adding.
  • Communication key: Set the key configured in central unit in the satellites.
  • Wireless planning: Perform range/coverage test before mounting; aim for RSSI > -85 dBm.
  • Check RSSI in KentixONE (multiple bookings/transmission cycles); test with original components; test mounting direction.
info

Strictly observe safety and environmental conditions during installation (ESD, protection class, temperature/humidity). Clearly label connections and addresses.

Checklist Steps​

1. Preparation and Planning​

  • Check release notes and compatibility (devices/firmware/licenses)
  • Provide/assign firmware packages and licenses
  • Define power/network topology (PoE, IP, VLAN, wireless/bus)
  • Plan support channels (hotlines, booked assistance registered)
  • Commissioning PC prepared (TeamViewer, update access)
  • Documentation/requirements spec/floor plans complete
  • Skill set/specialists clarified

2. Network and Infrastructure​

  • Customer network available and tested
  • VLANs pre-configured, port assignments documented
  • Firewall rules verified (Port 443 in/out, devices reachable)
  • Manageable PoE switches available; access data known
  • IP plan created (addresses, netmask, gateway, hostnames)

3. Device Preparation​

  • Components inventoried and function tested
  • Special configurations built and verified in advance
  • Uniform software version defined for all devices

4. Installation and Setup of Central Unit (always first)​

  • KentixONE central unit (SiteManager or Docker) installed and configured
  • Internet access of central unit verified
  • KentixONE license installed and activated

5. Prepare Satellites​

  • Set communication key in installation wizard (according to central unit)
  • Align firmware versions:
  • Sub-minor (e.g. 8.5.x) updates right after adding in KentixONE
  • Minor (e.g. 8.x.x) updates directly on device before adding
  • Add and configure satellite in central unit

6. Wireless Components (BLE/868 MHz)​

  • Perform range/coverage test before final installation
  • Check RSSI values in KentixONE (> -85 dBm)
  • Measure multiple bookings/transmission cycles
  • Test mounting direction with original components

7. Installation and Labeling​

  • Observe safety and environmental conditions (ESD, protection class, temperature/humidity)
  • Verify power supply
  • Label all connections and addresses clearly

8. Initial Configuration​

  • Structured initial configuration of devices in KentixONE
  • Implement parameters according to requirements spec
  • Set up communication paths to external services (SMTP, LDAP/AD, VDS)

9. Tests and Verification​

  • Perform function and tamper tests
  • Verify alarm paths (signaling, escalation)
  • Check and secure log/backup

10. Handover to Operations/Monitoring​

  • Logging completed; backup created
  • Handover incl. IP plan, access data, documentation
  • Monitoring activated; declare system operational after verified alarm paths

11. External Services​

  • SMTP: Server/Port/StartTLS/Authentication method tested
  • LDAP/AD: Base DN/Bind User/Filter tested
  • VDS/other: Endpoint/Token verified
tip

Keep all decisions and measurement results (e.g. RSSI, ports, VLANs) in this checklist or project protocol. This facilitates later maintenance and support.

Quick Reference (to fill in)​

IP Plan (Excerpt)​

DeviceHostnameIP Address/VLANGatewayLocation/Rack/HENote
Central
Satellite 1
Satellite 2

Alarm Test (Example Protocol)​

TestTriggerExpectedResultTimeOK
Tamper Sat-1Open coverAlarm + Email
TemperatureThreshold exceededAlarm + Escalation